Australian Tin Resources Pty Ltd

Update

Background

Contained Tin Value

Resources

Contact Us

Update – 31 July 2024

 

ATR is actively progressing its planned Rehabilitation and Tailings Reprocessing Project at the Ardlethan Tin Mine and is making good progress with pilot plant R&D activities at the site.

 

Earlier this year we installed a multi-gravity separator MGS) aimed at capturing and increasing the grade of tin concentrate that would otherwise be lost to the tailings waste stream after processing over the shaking tables. Commissioning of the MGS has demonstrated very encouraging results.

 

We are now contemplating the installation of a ball mill to process the approx. 50% of tailings volume presently not captured by the Derrick and Landsky screens at the front end of the process circuit. Assuming this proves successful, we will be able to more fully utilize the 30tph design capacity of the existing processing circuit and significantly increase grades and recoveries of tin (Sn) concentrate for sale to the overseas smelter.

 

However, rather than processing the entire tailings oversize volume through the ball mill, we are first investigating if we can reduce the volume fed to the ball mill and from the ball mill to the spirals, using preconcentration technologies to capture and upgrade the <125 micron tailings feed containing about 0.11% Sn, and screen out the >125 microns which contains little tin. 

 

To achieve this, we envisage a two-step process involving one of three, or potentially four, technologies, aimed at providing up to a 4 times upgrade of the tailings oversize, with 80% Sn recovery. Towards this end, this month we have sent samples of the oversize tailings to Gekko to test the upgrade and recovery they can achieve with their in-line pressure jig (IPJ), to Newcastle University to test the FL Schmidt reflux classifier, and to Mineral Technolgies, to test whether additional spirals might be added to the existing circuit. We have also revisited previous test results of the Falcon classifier, because unlike previous Falcon testing targeting ultra-fine tin tailings (<106 microns), we are now targeting the >106 micron fractions which we understand is potentially a sweet spot for the Falcon.

 

Subject to satisfactory test results, and having regard to the cost benefit and schedule, we will install one of the above contenders into the process circuit as soon as possible.

 

With about six months to procure the equipment and complete the installation, it will not be until the end of 2024 that we will be able to more fully utilise the production capacity of the existing 30 tph spiral plant and commence full scale commercial production. 

 

During pilot plant testing we have been working relatively low hours per week to minimise costs and process water consumption while we investigate process refinements and improvements to plant reliability and performance. However, we have recently been increasing plant working hours as concentrate production volumes, Sn grades and recoveries improve.  With installation of the ball mill, we will be on the cusp of finalizing commissioning of the existing 30 tph plant and commencing full-scale commercial production, albeit we will still have further improvements to the process circuit to be trialled after production operations formally commence.  In the meantime, by working additional plant hours, we expect the operation to be cash flow positive.

 

During our pilot plant R&D activities we have so far sent eight shipments of concentrate to market for assessment and have been able to progressively increase the grade and purity and hence the value of each shipment as a result of improvements in the pilot plant process circuit initiated by our R&D program.  We are expecting the 9th concentrate shipment to be despatched to the overseas smelter in late-August 2024.

 

Commencing with shipping one 22 tonne container load of concentrate (20 tonnes dry weight, containing over 50% tin) to market overseas each month, ATR’s intention is to progressively ramp up production as we become increasingly satisfied that the production process circuit is as efficient and reliable as we can reasonably achieve and is operating on a financially viable basis. We are presently on the cusp of this objective.  We will do this in a step-by-step manner as potential process improvements are tested and implemented, by increasing hours worked each week and by adding additional production capacity to the plant process circuit.

 

We have submitted all environmental plans and other data to the various government authorities as required by Council’s Development Approval Conditions of Consent for a 1.5 million tonne per annum operation and have all necessary approvals, including Environmental Protection Licence Number 21797 granted to us on 6 July 2023, so there are no regulatory impediments to our commencing full scale production operations whenever it suits us.

 

IMG_0828.jpg

 

IMG_0826.jpg

Back to top

 

 

Background

 

The Ardlethan Tin Mine is located approximately 500 km southwest of Sydney, NSW, 5 km NW of Ardlethan township. It covers about 400 hectares on land wholly owned by EOE (No 75) Pty Ltd (EOE), a wholly owned subsidiary of Australian Tin Resources Pty Ltd (ATR).

 

Excellent road and rail access is available within close proximity to the site. Additionally, an approx.50km pipeline from the Murrumbidgie River at Grong Grong to site is now decommissioned, but subject to approval could potentially be reinstated if required.

 

 

The plant is presently powered by diesel generators. However, there is an electrical substation in Tin Mine Road, about 2.0km from the mine site, should ATR wish to reconnect to the main electricity grid.

 

Mining at Ardlethan commenced in 1912. At first it was on a small scale, but between 1965 and 1986 Aberfoyle Resources NL around 30 million tonnes of granite, initially from open cut operations and later from underground workings.  Mining operations ceased in 1986 due to the collapse of tin prices.

 

Of the approx 30 million tonnes mined, Aberfoyle processed about 9.0m tonnes of ore assaying 0.46% tin. The remaining 21 million tonnes (approx) had a tin content below Aberfoyle’s cut-off grade of 0.20% tin and was stockpiled in overburden waste dumps which surround the open cuts. In 2020 ATR carried out very successful tests offsite to trial a Tomra Ore Sorter on a bulk sample of our waste rock. The results were impressive with high upgrade rates being achieved and pointed to the feasibility of viably processing the waste rock as a future option.

 

Additionally, the under-explored underground Ardlethan tin mine hard rock resource offers an attractive future opportunity in the longer term.

 

Significant tin deposits have also been identified by exploration drilling in potentially available leases adjacent to the Ardlethan Tin Mine site.

 

Image preview

 

Back to top

 

 

Contained Tin Value

JORC certification and Ardlethan Tin Mine records show there is at least 66,500 tonnes of contained tin on site. At the current tin price of US$30,000/ tonne (A$47,000/tonne) this represents a value of over A$3,000 million – a very worthwhile value proposition.

The defined deposit places it in the top twenty tin mines in the world.

Importantly, the mine is being developed and operated by ATR on the existing mine site previously operated by Abefoyle until 1986.  Unlike many resource undertakings in Australia, ATR already has its approvals in place and does not need to embark on the very onerous and expensive development consent and environmental approval process required when a proposed mining undertaking seeks to transition from exploration to production.

The tin on the Ardlethan site is contained in three areas as shown in the Resources summary below and more fully described in the Resources section of this website.

Total Resources

Tonnes
(million)

%Sn

Contained Tin

(tonnes)

A$ Value
(Based on Current tin price of US$30,000/tonne

Tailings *

10.7

0.20%

21,600

A$ 982 million

Waste Material *

21.3

0.09%

20,200

A$ 918 million

Hard Rock Underground **

5.5

0.45%

24,700

A$ 1,122 million

TOTAL

37.5

 

66,500

A$3,022 million

*     Source: Reynard Australia Pty Ltd JORC Report, October 2011

**  Source: Ardlethan Information Brochure, Molina & Doran, May 1989

When the mine capacity and production is expanded to full operations, the operating cost is expected to be in the bottom quartile of global tin mining operating costs.

Tin is around 30 times rarer than copper and all tin mines operating today are based on brownfield mining operations. No new tin resource has been found anywhere in the world in more than 50 years. The Ardlethan tin mine dates back to 1912 with artisanal mining operating on the site from the nineteenth century.

The International Tin Association is predicting a shortfall in tin supply deficit from next year (2025) driven by supply constraints from existing operators and the growing demand for tin in Electric Vehicles and Solar panels.

As summarised in the Introduction Section above, there have been some challenges in extracting the tin from the tailings which have a grade of only 0.2 percent tin. The company has been conducting research and development activities based on the 2016 engineering and assessment of Mineral Technologies, a respected global leader in the use of spirals to upgrade and extract the tin contained in the tailings to a saleable grade of 50+% tin concentrate. This has been successful with eight shipments sent, accepted and paid for by Chinese smelters to date using our 15-30 ton per hour Pilot processing plant

Current research and development activity is focused on increasing capacity, recovery and grade from the existing 30 tonne / hour pilot plant by introducing refinements in the processing circuit in a step by step manner. We are presently planning to crush the oversize tailings oversize which is currently not being processed but contains usable tin. This will be followed by further capacity increases that will drive the cash operating cost below the lowest quartile of production costs for global tin producers. The research focus is to have a cash operating cost below US$10,000 a tonne of tin produced.

Our current approvals are for re-processing tailings. However, there may be further opportunity to increase production by processing the above ground waste rock which contains approximately A$1 billion of tin. Research using Tomra ore sorting technology has shown this to be a tantalizing option for the future.

Finally, the development of the underground resource on our site, and potentially expanding from our site into known resources neighbouring our leases, would require significant capital and new approvals, but is technically straight forward. It is likely this option would be undertaken by a larger and more experienced mining operator.

Back to top

 

 

Resources

 

1.       Tailings

Retreatment of the tailings from previous mining operations was the main driver for Australian Tin Resources deciding to acquire the Ardlethan tin mine.

 

ATR now has DA approval to construct a 150 tonne per hour plant on site to operate 24 hours/day, 7 days/week.

 

However, before moving to full scale production, ATR is firstly carrying out small scale pilot plant processing operations on site to prove up and refine the processing technology.

 

We will the upsize the plant from 30 tonnes per hour, to 60 tonnes per hour, and ultimately to it’s approved 150 tonnes per hour capacity over time.

 

 

 

Tailings

JORC Resource

Inferred Resources

Indicated Resources

Contained Tin (tonnes)

Tonnes

millions

% Tin

Tonnes

millions

% Tin

Main Tailings Dam

Pre 1964

Post 1964

 

1.94

 

0.30%

 

4.87

 

 0.19%

 

5,800

9,000

Spring Valley Tailings Dam

Pre 1981

Post 1981

 

 

2.67

0.48

 

 

0.17%

0.14%

 

 

 

 

4,500

700

White Crystal Pit Tailings

0.76

0.15%

 

 

1,100

Sulphide Tailings Dam

0.03

1.53%

 

 

500

TOTAL TAILINGS

5.86

0.21%

4.87

0.19%

21,600

    Source: Reynard Australia Pty Ltd JORC Report, October 2011

 

2.       Waste Stockpiles

 

The Ardlethan mine contains approximately 21.3 million tonnes of granite previously mined by Aberfoyle and now stored in waste dumps circling the open cuts. Processing the stockpiled waste material represents a potential option and is a comparatively low capital and operating costs option. Waste material boulders typically range in size from approx 30cm to 100cms in diameter and the waste dumps are readily accessible from existing mine haul roads.

 

ATR has obtained JORC certification of the waste material resources stockpiled at the mine site as summarized in the table below.

 

In 2020 ATR carried out very successful tests offsite to trial a Tomra Ore Sorter on a bulk sample of our waste rock. The results were impressive with high upgrade rates being achieved and pointed to the feasibility of viably processing the waste rock as a future option.

 

 


Waste Stockpile

JORC Resource

Inferred Resources

Indicated Resources

Contained Tin

(tonnes)

Tonnes

millions

% Tin

Tonnes

millions

% Tin

Main Waste Dump

Pre 1964

Post 1964

 

 

0.33

18.72

 

 

0.10%

0.09%

 

 

 

 

300

17,400

White Crystal

2.20

0.11%

 

 

2,500

TOTAL WASTE

21.25

0.09%

 

 

20,200

Source: Reynard Australia Pty Ltd JORC Report, October 2011

 

3.       Hard Rock Mining of Underground Resource

 

The table below summarises the hard rock mineral resources at the time of mine closure in August 1986. These resources consist of broken ore in stopes, remnants, pillars and resources inferred from drilling. Access would be via a decline just north of the main Ardwest / Wild Cherry Open Cut.

 

There is further potential deeper underground on the mine site and in surrounding environs. There are also some small deposits of known high grade ore at or near the surface.

 

Hard Rock Underground Resource

 

Inferred Resources

Indicated Resources

Contained Tin (tonnes)

Tonnes

millions

% Tin

Tonnes

millions

% Tin

Measured

.05

0.51%

275

Indicated

.80

0.50%

3,980

Inferred

0.47

0.36%

1,670

Potential

 

 - Black Reef / Champion

 - Godfrey

 - Keogh East

 

0.28

3.80

0.10

 

0.83%

0.42%

0.50%

 

2,325

15,950

500

TOTAL HARD ROCK

4.64

0.44%

0.85

0.50%

24,700

Source - Ardlethan Information Brochure, Molina & Doran, May 1989.

 

 

Back to top

 

 

Contact Us

 

Australian Tin Resources Pty Ltd

ABN 17 124 654 360

 

Registered Office:

Level 4, 141 Walker Street

North Sydney, NSW 2060

(PO Box 1506, North Sydney, NSW 2059).

Australia

Phone  +61-2-9959 5599

 

Site Office:

Tin Mines Road,

Ardlethan, NSW 2665)

(PO Box 13, Ardlethan, NSW 2665)

Australia.

Phone 0437 772 256

 

 

Complaints:

Phone 0437 772 256

Email: admin@atresources.com.au

 

Contacts:

 

Peter Francis - Director

Mobile  0412 178 128

Email: pfrancis@atresources.com.au

 

 

Glen Cunningham - Director

Mobile 0412 058 773

Email: gcunningham@atresources.com.au

 

 

Bill Lannen - Director

Mobile 0418 330 583

Email: blannen@atresources.com.au

 

 

Sam Boatwright - Site Manager

Mobile 0413 483 324

Email: samb@atresources.com.au

 

 

 

Back to top